3/1/02

The chimney materials have started to arrive!

The cement blocks and flue sections
 ...and some of the bricks
The bricks are used / recovered, and have nice color and "character"

Click on any of the following pictures for a larger view:

Front

Temporary steps -- no more walking the plank!

Siding is on the back wall

Some siding done on side wall

Plumbing is being roughed in

The tub has arrived

The generator is here!

Inside view of generator

Framing for bookcases in stairway


3/8/02

Front

Mason building the chimney base

Chimney - cellar

Electrical Conduit - boxed and attached to house

Electrical Panel - roughed

Front trim is done

Gable is trimmed

Right - trim is done, exterior light roughed in

Soffit trim and vents done, Exterior light roughed

Propane heater in cellar keeps everything warm - including Anna

Snow and Sun?!


3/22/02

Front

Chimney is partially complete

Wood stove brickwork

Insulation and strips in front room

Insulation - upstairs

Insulation - Lis' upstairs office

Upstairs Bathroom - plumbing, electrical, insulation

Posts for entrance


3/29/02

Front

Drywall truck

Upstairs drywall

Kitchen - drywall is up

Warren's Office

Media Room - extra boards for projector mount

Electrical Panel - temporary circuits are attatched to generator

Water Tank

Slate Tiles are here

Slate Tile closeup

Anna keeps watch on septic system

One of the open-top culverts for the driveway (upside-down)


Back to Index