3/1/02
The chimney materials have started to arrive!
| The cement blocks and flue sections |
 |
| ...and some of the bricks |
 |
| The bricks are used / recovered, and have nice
color and "character" |
 |
Click on any of the following pictures for a larger view:
|
|
|
Front
|
|
|
|
Temporary steps -- no more walking the plank!
|
|
|
|
Siding is on the back wall
|
|
|
|
Some siding done on side wall
|
|
|
|
|
Plumbing is being roughed in
|
|
|
|
The tub has arrived
|
|
|
|
The generator is here!
|
|
|
|
Inside view of generator
|
|
|
|
|
Framing for bookcases in stairway
|
|
|
3/8/02
|
|
|
Front
|
|
|
|
Mason building the chimney base
|
|
|
|
Chimney - cellar
|
|
|
|
Electrical Conduit - boxed and attached to house
|
|
|
|
|
Electrical Panel - roughed
|
|
|
|
Front trim is done
|
|
|
|
Gable is trimmed
|
|
|
|
Right - trim is done, exterior light roughed in
|
|
|
|
|
Soffit trim and vents done, Exterior light roughed
|
|
|
|
Propane heater in cellar keeps everything warm - including Anna
|
|
|
|
Snow and Sun?!
|
|
|
3/22/02
|
|
|
Front
|
|
|
|
Chimney is partially complete
|
|
|
|
Wood stove brickwork
|
|
|
|
Insulation and strips in front room
|
|
|
|
|
Insulation - upstairs
|
|
|
|
Insulation - Lis' upstairs office
|
|
|
|
Upstairs Bathroom - plumbing, electrical, insulation
|
|
|
|
Posts for entrance
|
|
|
3/29/02
|
|
|
Front
|
|
|
|
Drywall truck
|
|
|
|
Upstairs drywall
|
|
|
|
Kitchen - drywall is up
|
|
|
|
|
Warren's Office
|
|
|
|
Media Room - extra boards for projector mount
|
|
|
|
Electrical Panel - temporary circuits are attatched to generator
|
|
|
|
Water Tank
|
|
|
|
|
Slate Tiles are here
|
|
|
|
Slate Tile closeup
|
|
|
|
Anna keeps watch on septic system
|
|
|
|
One of the open-top culverts for the driveway (upside-down)
|
|
|
Back to Index